This is the average cost of painting materials prices in National Capital Region. The materials below are the most common materials needed in your DIY painting projects.
Materials Description
Unit
Ave. Price (PhP)
Paint Tinting Color
L
55.00
Paint Aluminum
Gal
570.00
Paint Enamel
Gal
598.00
Paint Latex Gloss
Gal
573.00
Paint Latex Semi-Gloss
Gal
573.00
Paint Red Lead
Gal
391.00
Thinner Paint
Gal
283.00
Thinner Lacquer
Gal
231.00
Paint Metal Epoxy
Gal
665.00
Paint Primer Solvent
Gal
527.00
Brush Paint – 2″
pc
37.00
Brush Paint – 3″
pc
51.00
Brush Paint – 4″
pc
68.00
Brush Roller #9 with Tray
pc
146.00
Steel Brush – 4″
pc
86.00
Oil Paint
L
92.00
Lacquer Putty
Kg
162.00
Sand Paper #120
Dozen
130.00
Spar Varnish
L
127.00
All amount in Php. To see all the material prices we have posted click here.
SUBSCRIBE to keep posted and follow us on Facebook. Let us know how this blog helped you by hitting like or share!
This is a small house, thus, for small family, a 4-person home for people who are just starting to settle down. Construction of houses in the Philippines may vary. A lot of factor plays for the total construction cost of a house. The most common determinant is the area, the aesthetic, meaning, the materials used, and the location.
This guide will help you determine the total cost to build your own home from start to finish.
Bungalow Dos – Perspective Plan
This is a 76 square meter house. There are two bedrooms with single car park.
The balcony and the house is elevated at 0.20 meters. Low-cost materials were used during the designing and estimation, but the structural credibility is not compromised.
All floors were tiled. The balcony has enough area for visitors and family dinners. The idea is to provide enough space to “breathe”. Perfect for barbeque parties and socializing. There are two comfort rooms, one is common and the other is on master’s bedroom. Service area is located at the rear portion of the house with sink.
We’ve scouted a site with good customer reviews for their hand tools on this site, they ship nationwide!
Below is the estimated cost of Bungalow Dos construction from start to finish.
Activity / Construction Trade
Amount (PhP)
Percentage
Manual Excavation and Backfilling
9,082.29
0.92%
Concreting Works (Rebars, Concrete, Formworks, Gravel Bed)
304,761.76
30.79%
Masonry Works
107,610.94
10.87%
Plastering Works
40,913.27
4.13%
Ceiling Works
74,719.53
7.55%
Concrete Painting
45,091.65
4.56%
Ceiling Painting
50,737.22
5.13%
Metal Painting (Truss / Roof)
20,173.27
2.04%
Tiling Works
63,928.98
6.46%
Roofing Works
109,652.71
11.08%
Hardware
7,231.25
0.73%
Doors, Windows, and Railings
66,709.20
6.74%
Plumbing Works
66,630.00
6.73%
Electrical Works
22,479.60
2.27%
TOTAL
989,761.67
100.00%
Bungalow Dos – Sample Bill of Quantity
Get the complete plan (pdf, short bond paper size) with Bill of Materials (excel) incorporated with labor calculations. Just input the labor rates in your area, prices of the materials and viola! You’ll get the total amount and the time needed to complete certain works. More details HERE. or know more on how to pay via Gcash here.
Just in case you’re searching for high-class but affordable wall arts to brighten up your wall, you may want to check this site, highly-recommended (and they ship nationwide!).
Bungalow Dos Bundle Amount : Php 850.00
Pay via GCASH at 0920-591-0982 care of RGM, download via Google Drive.
Inclusions:
Bill of Materials (How many bags of cement, tiles, reinforcing bars will you need) with Labor timeline estimates (How many hours for a foreman, skilled and unskilled workers are needed to complete a certain work).
2. Floor plan, perspective and elevations.
3. Power and lighting layout.
4. Sanitary and waterline layout with Septic and Grease Trap Details.
5. Foundation Plan.
6. Column, Footing and Beam Details.
7. Roof Framing and Beam Plan.
Limitations: This excel file will only work for this set Plan. Labor calculations are pre-assumed based on average productivity rate of laborers in the Philippines.
Exclusions: Structural Calculations. Sign and seal of Professional Engineer / Architect.You cannot use this to apply for building permit unless re-drawn, signed and sealed by a professional.
Disclaimer: The plans are just guides. That is why it is cheap. Though the structural concepts, depths of foundations, beams and column sizes, reinforcing bars are considered with our intellect and experience as licensed civil engineers, it is ALWAYS advisable to hire a professional that you trust to design your homes, construct the plans at your own risk.
If you have any questions email us at philconprices@gmail.com .
Let us know how this post helped you by commenting. Stay safe!
Average admixtures and curing material prices for National Capital Region. These chemicals are added to freshly batched or hardened concrete to enhance its properties. Â
Materials Description
Unit
Ave. Price. (PhP)
Concrete Accelerating Admixture
L
103.00
Concrete Accelerating Admixture
Bag
276.00
Concrete Retarding Admixture
L
41.00
Concrete Retarding Admixture
Bag
364.00
Concrete Water-Reducing Admixture
L
60.00
Concrete Water-Reducing Admixture
Bag
285.00
Concrete Water-Reducing and Accelerating Admixture
L
109.00
Concrete Water-Reducing and Accelerating Admixture
Bag
428.00
Concrete Water-Reducing High Range Admixture
L
65.00
Concrete Water-Reducing High Range Admixture
Bag
247.00
Concrete Water-Reducing and Retarding Admixture
L
120.00
Concrete Water-Reducing and Retarding Admixture
Bag
490.00
Concrete Water-Reducing, High Range and Retarding Admixture
L
89.00
Concrete Water-Reducing, High Range and Retarding Admixture
Bag
445.00
Water-Proofing Cement (SAHARA or Equivalent)
Bag
45.00
The concrete additives and admixtures prices here are just average price in the market. Thus, prices may be lower or higher in actual. All amount in Philippine Peso. To see all the material prices we have posted click here.
SUBSCRIBE to keep posted and follow us on Facebook. Let us know how this blog helped you by hitting like or share!
Average construction material prices for National Capital Region Timber Formworks.
Materials Description
Unit
Average Price (PhP)
Coco lumber
bd. ft.
62.00
3/4″ x 4′ x 8′ – Plyboard
pc
1,074.00
1″ x 4′ x 8′ – Plyboard
pc
1,138.00
1/4″ x 4′ x 8′ – Marine Plywood
pc
435.00
1/2″ x 4′ x 8′ – Marine Plywood
pc
790.00
3/4″ x 4′ x 8′ – Marine Plywood
pc
1,374.00
1/4″ x 4′ x 8′ – Ordinary Plywood
pc
381.00
1/2″ x 4′ x 8′ – Ordinary Plywood
pc
674.00
3/4″ x 4′ x 8′ – Ordinary Plywood
pc
1,112.00
Assorted Nails
Kg
65.00
All amount in Php. To see all the material prices we have posted click here.
The construction materials above are the most common materials needed for timber formworks and scaffolds. The prices here are average, meaning, construction materials prices may be higher or lower in actual.
SUBSCRIBE to keep posted and follow us on Facebook. Let us know how this blog helped you by hitting like or share!
TRENCHING & BACFILLING OF UNDERGROUND PIPING USING EXCAVATION MATLS MANUAL FROM:
0 – 2m Depth
1.25
MH/LM
2 – 3m Depth
1.67
MH/LM
3 – 4m Depth
2.50
MH/LM
4 – 5m Depth
3.33
MH/LM
Placing binder gravel
0.11
MH/M3
Escombro or Debris backfilling
0.21
MH/M3
Spreading, tamping & grading
0.48
MH/M2
Mechanical compaction, plate compaction
0.06
MH/M3
MANUAL CLEARING & GRUBBING
Clearing under growth & trees – 12″
0.05
MH/M2
Clearing under growth & shrubs
0.03
MH/M2
Disposal of soil
1.69
MH/M3
Hauling of soil
1.00
MH/M3
Gravel fill
2.07
MH/M3
EXCAVATION – CRANE & CLAMPSHELL
With 8 men & 2 carpenters
1.07
MH/M3
5.ROOFING AND SIDING
Roofing
Metallic
0.97
MH/m2
Non-Metallic
1.51
MH/m2
Siding
Metallic
1.29
MH/m2
Non-Metallic
1.51
MH/m2
CONCRETE WORKS
4.CONCRETE WORKS
Grade members
Formworks
2.54
MH/M2
Concreting
8.54
MH/M3
Rebar
0.07
MH/kg
Finishing
0.40
MH/M2
Suspended members
Formworks
3.28
MH/M2
Concreting
16.70
MH/M3
Rebar
0.08
MH/kg
Finishing
0.80
MH/M2
Embedded metal
0.27
MH/kg
Water proofing
1.82
MH/M2
Joint filler
0.30
MH/lLm
PLACING CONCRETE
Slab on Fill
5.00
MH/M3
Slip Form
25.00
MH/M3
Floor Finish Unhardened
1.00
MH/M3
Concrete finished hardened
1.43
MH/M3
REBAR WORKS
Ground floor installation
0.07
MH/M3
Upper floor installation
0.08
MH/M3
Fabrication
0.10
MH/M3
Mixing manual
16.00
MH/M3
Mixing machine
1.80
MH/M3
MORE THANÂ 1.8 M3 POUR
Chute from truck
7.00
MH/M3
Crane & bucket
14.00
MH/M3
Wheeling
27.00
MH/M3
Finishing
2.80
MH/M3
FORMWORKS & CARPENTRY WORKS
FORM WORKS INSTALLATION
Wall on ground
2.00
MH/M2
Wall above ground
2.35
MH/M2
Beams
3.08
MH/M2
Columns
2.35
MH/M2
Suspended slab
Suspended slab 0 – 18″
1.67
MH/M2
Suspended slab 10 – 36″ up
3.33
MH/M2
Elevated & shored slab forming
Forming only
8.60
MH/M2
Forming & Shoring
11.00
MH/M2
Wood wall & Partition
0.50
MH/M2
FORM WORKS FABRICATION
Form works fabrication
1.00
MH/M2
STRIPPING OF FORMS
Wall on ground
0.25
MH/M2
Wall above 10″
1.29
MH/M2
Beams
1.03
MH/M2
Columns
0.85
MH/M2
Suspended slab
Suspended slab 0 – 18″
0.83
MH/M2
Suspended slab 10 – 36″ up
1.08
MH/M2
Elevated & shored slab forming – strip of forms
3.50
MH/M2
Floor slab at grade – strip of forms
2.80
MH/M2
INSTALLATION OF CARPENTRY WORKS
Plywood partition
1.00
MH/PC
T & G Flooring and Siding
0.14
MH/B.F.
Ceiling & frame work
0.36
MH/B.F.
Siding frame work
0.27
MH/B.F.
Flooring framing
0.97
MH/B.F.
Wooden post erection
0.43
MH/B.F.
Truss Fabrication
0.35
MH/B.F.
Truss Installation
0.80
MH/B.F.
Girt Installation
0.21
MH/B.F.
Plates Installation
0.13
MH/B.F.
Purlins Installation
0.27
MH/B.F.
Fascia board Installation
0.46
MH/B.F.
1/4″ or 3/4″ thk. plywood
Cutting by manual
1.00
MH/PC
Assembly
0.42
MH/M2
ARCHITECTURAL SPECIALTIES
DOORS
Wooden
2.37
MH/M2
Steel
7.64
MH/M2
Aluminum
8.07
MH/M2
Cyclone wire
7.64
MH/M2
WINDOWS
Glass
3.23
MH/M2
Louver
4.63
MH/M2
Steel
32.29
MH/M2
PARTITIONS
single wall
2.48
MH/M2
Wooden wall
3.44
MH/M2
Wooden Louver
3.44
MH/M2
cyclone Louver
5.38
MH/M2
PAINTING ( 3 coats )
Equipment
0.24
MH/f2
Pipes
0.30
MH/f2
Miscellaneous
0.24
MH/f2
STRUCTURAL STEEL WORKS
7. STRUCTURAL STEEL
Fabrication
Light
110-130
MH/MT
Heavy
60-90
MH/MT
Erection
Light
70-100
MH/MT
Heavy
40-60
MH/MT
WELDING ( one pass only )
1- Welder and 1- Helper ( 16 total mh )
40-50
Lf/day
G.1 STRUCTURAL STEEL
Fabrication
Heavy weight
50-90
MH/MT
Light weight
100-125
MH/MT
Grating 1 1/4″ x 3/16″
3.0 – 3.5
MH/SF
Star threat grating
4.0 – 5.0
MH/SF
Erection
Heavy Structural teel
30 – 60
MH/MT
Light Structural steel
60- 90
MH/MT
Stacks ( Inc. full welding )
250 – 300
MH/MT
Tanks ( Inc. full welding )
200 – 275
MH/MT
FINISHING AND MASONRY WORKS
H. CHB
4” CHB
Laying
8.0 – 10
m2/day
Tooling
11 – 14
m2/day
Plastering
8.0 – 10
m2/day
6” CHB
Laying
7.0 – 9.0
m2/day
Tooling
11 – 14
m2/day
Plastering
8.0 – 10
m2/day
8” CHB
Laying
6.0 – 8.0
m2/day
Tooling
11 – 14
m2/day
Plastering
8.0 – 10
m2/day
These are average productivity ratios of an average construction worker. Productivity ratios of manpower and equipment are used in the construction industry to estimate how much time is needed to complete a certain work.
Check this if you are looking for in-budget but outstanding quality powertools.
To see all the material prices we have posted click here.
Please let us know how this blog helped you by subscribing, hitting like or share!
People has been asking for a typical amount needed to construct a boarding house so here it is. We know how hard it can be when you don’t have any technical person to ask to. We hope this post will be of help.
The plan and perspective below comes with its corresponding bill of quantity with prices.
4″ hollow blocks are used for the entire walls. Solid doors for the main door and PVC door for the comfort room. All part of this house is plastered and painted.
All floors are calculated to be tiled, so with the sink and its splashboard. Comfort rooms are also tiled with its walls.
Single family septic tank is used as its septic vault. It is anticipated that only students (one person per room) will be the occupants. Windows are all aluminum sliding except for the awning window on the toilets. Interior ceiling is plywood, toilet and exterior ceiling are fiber cement board.
We’ve scouted a site with good customer reviews for their hand tools on this site, they ship nationwide!
Only one metering system is set for the electrical. Thus, each rooms will have its own submeters. Same goes with the water, but with no submeter. It is assumed that the landlord will have a fixed payment for the water bill per occupant.
Bungalow Uno – 36 SQM House at 495K Total Construction PriceBungalow Dow – 2BR with Carpark under 1M total construction price
Four-Bedroom Boarding House Bill of Materials Summary below.
Excavation (and backfilling)
9,230.93
1.42%
Gravel Bed
4,638.18
0.72%
Concrete
55,701.33
8.60%
Reinforcing Bars
55,239.35
8.52%
Formworks
16,695.12
2.58%
Masonry Works
51,414.03
7.93%
Plastering Works
32,771.61
5.06%
Ceiling Works
56,132.02
8.66%
Painting Works
69,501.62
10.73%
Septic Tank
19,598.36
3.02%
Tiling Works
48,278.04
7.45%
Roofing Works
56,161.12
8.67%
Doors
29,223.49
4.51%
Windows
29,301.13
4.52%
Hardware
11,570.12
1.79%
Plumbing Works
59,957.25
9.25%
Electrical Works
42,600.80
6.57%
TOTAL
648,014.41
100.00%
All amount are in Philippine peso.
Get the complete plan (pdf, short bond paper size) with Bill of Materials (excel) incorporated with labor calculations. Just input the labor rates in your area, prices of the materials and viola! You’ll get the total amount and the time needed to complete certain works.
Click hereto pay via PayPal (you’ll get the excel and pdf right away).
Come here instead if you want to pay via GCash (manual downloading via Google Drive).
Just in case you’re searching for high-class but affordable wall arts to brighten up your wall, you may want to check this site, highly-recommended (and they ship nationwide!).
Four Bedroom Boarding House Bundle Amount for only Php 500.00
Inclusions:
Bill of Materials (How many bags of cement, tiles, reinforcing bars will you need) with Labor timeline estimates (How many hours for a foreman, skilled and unskilled workers are needed to complete a certain work).
2. Floor plan, perspective and elevations.
3. Power and lighting layout.
4. Sanitary and waterline layout with Septic and Grease Trap Details.
5. Foundation Plan.
6. Column, Footing and Beam Details.
7. Roof Framing and Beam Plan.
Limitations: This excel file will only work for this set Plan. Labor calculations are pre-assumed based on average productivity rate of laborers in the Philippines.
Exclusions: Structural Calculations. Sign and seal of Professional Engineer / Architect.You cannot use this to apply for building permit unless re-drawn, signed and sealed by a professional.
Disclaimer: The plans are just guides. That is why it is cheap. Though the structural concepts, depths of foundations, beams and column sizes, reinforcing bars are considered with our intellect and experience as licensed civil engineers, it is ALWAYS advisable to hire a professional that you trust to design your homes, construct the plans at your own risk.
Let us know how this post helped you by commenting. Stay safe!
So, a lot of readers were asking for house construction prices. True to our mission to help ordinary Filipinos get a clear idea on how much houses are constructed, this post should help you.
The perspective below comes with its bill of quantity with percentage breakdown and floor plans.
The total price below may be higher or lower depending on the materials you will be using and the labor rates in your area. The depth of foundation is at 0.70m from the natural ground line to help with the structural integrity considering nowadays that we are experiencing crazy climate change aftermath.
The windows are all aluminum sliding except for the toilet that is awning. Solid core doors are set for exterior doors main and rear), hollow ones are for the bedrooms. PVC door for the toilet room.
We’ve scouted a site with good customer reviews for their hand tools on this site, they ship nationwide!
6″ concrete hollow block for all exterior walls and 4″ for the interior. Fiber cement board ceiling for exterior and toilet while plywood for interior, all with aluminum framing. The roof framing are all steel.
Four – Bedroom Boarding House – 650k Total Construction Price
Get the complete plan (pdf, short bond paper size) with Bill of Materials (excel) incorporated with labor calculations. Just input the labor rates in your area, prices of the materials and viola! You’ll get the total amount and the time needed to complete certain works. More details HERE. or know more on how to pay via Gcash here.
Bungalow Uno Bundle Amount : Php 350.00
Inclusions:
Bill of Materials (How many bags of cement, tiles, reinforcing bars will you need) with Labor timeline estimates (How many hours for a foreman, skilled and unskilled workers are needed to complete a certain work).
2. Floor plan, perspective and elevations.
3. Power and lighting layout.
4. Sanitary and waterline layout with Septic and Grease Trap Details.
5. Foundation Plan.
6. Column, Footing and Beam Details.
7. Roof Framing and Beam Plan.
Limitations: This excel file will only work for this set Plan. Labor calculations are pre-assumed based on average productivity rate of laborers in the Philippines.
Exclusions: Structural Calculations. Sign and seal of Professional Engineer / Architect.You cannot use this to apply for building permit unless re-drawn, signed and sealed by a professional.
Disclaimer: The plans are just guides. That is why it is cheap. Though the structural concepts, depths of foundations, beams and column sizes, reinforcing bars are considered with our intellect and experience as licensed civil engineers, it is ALWAYS advisable to hire a professional that you trust to design your homes, construct the plans at your own risk.
If you have any questions email us. We now offer signed and sealed plans for Building Permit Applications.
Let us know how this post helped you by commenting. Stay safe!