Average House Construction Cost Philippines

A lot of people were asking how much is the average construction cost of a house and we see that the internet does not give exact answer to this concern. If you are one of the non-technical person who wants bulls eye answer, then you are reading the right article.

The sample floor plan below comes with its own simplified Bill of Quantity. Check this average construction cost of 2-story house too! But if you are looking for a garage construction estimate alone, This one is the right guide for you.

This Bungalow Uno – 36 SQM below 500k might help you as well.

HOUSE 4-page-001
 Sample Floor Plan
Description % Total  Total Cost
Earthworks
Excavation & Embankment including Gravel Fill 6.42%              86,978.28
Structural Works
Structural Concrete (class A, 28 days) 18.45%           250,203.44
Reinforcing Bars 13.10%           177,668.24
Formworks and Falseworks 6.01%              81,450.71
Architectural Works
Cost of Ceiling – Fiber Cement Board 3.73%              50,506.60
Wooden Door (Flush and Solid Panel) 2.47%              33,436.31
Aluminum Glass Window (Awning and Fixed) 3.82%              51,751.60
Water Proofing, Cement Base 0.08%                1,138.37
Glazed Tiles and Trim 3.11%              42,187.80
Unglazed Tiles 0.61%                8,264.51
Cement Plaster Finish 2.45%              33,189.70
Masonry Works (including reinforcing steel) 6.09%              82,577.76
Interior and Exterior Painting Works 5.32%              72,145.15
Structural  Steel (for Truss Works) 5.36%              72,631.78
Roofing Works (Around 124 sq.m.) 6.72%              91,046.59
Sanitary and Plumbing Works
Sewer Line Works 5.09%              68,954.08
Plumbing Fixtures 2.07%              28,068.08
Cold Water Lines 0.61%                8,239.08
Storm Drainage and downspout 3.96%              53,678.14
Electrical Works
Conduits,Boxes & Fittings 0.80%              10,868.08
Wires and Wiring Devices 1.71%              23,196.84
Panel Board with Main & Branch Breakers 0.47%                6,310.80
Lighting Fixtures  and Lamps 1.57%              21,289.04
>>> Grand Total 100.00%        1,355,780.98

The prices comes with its corresponding labor and equipment costs. The materials used are for medium-cost house construction. The average  timeline for this type of house is around 4-6 months.

Check this post if you are looking for the average cost of construction your own septic tank.

If you are looking for a metal gate construction, click here.

We have also created posts that most people asks us about. Check it out below.

Roofing Works Materials Breakdown per Square Meter

Tiling Works Materials Breakdown per Square Meter

Ceiling Construction Materials Breakdown per Square Meter

If in doubt, it would still be advisable to hire a professional engineer or architect to look over your house construction.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!