Visayas Doors and Windows Prices

DOORS
Material Description Unit  Amount (PhP)
Accordion Type Door SQ.M.             2,198.28
Aluminum Glass Door SQ.M.             6,148.13
Flush Hollow Core Door SQ.M.                873.94
Flush Type Solid  Core Door SQ.M.             1,868.77
Glass Transom on Wood SQ.M.             1,897.48
Narra Paneled Door SQ.M.             5,504.32
Tanguile Paneled Door SQ.M.             4,140.01
Varifold Type Door SQ.M.             2,878.76
WINDOWS
Material Description Unit  Amount (PhP)
Aluminum Casement  Window SQ.M.             4,263.58
Awning Type Steel Casement Windows SQ.M.             1,959.80
Fixed Glass Window on Metal Frame SQ.M.                521.22
Fixed Louvered Steel Window SQ.M.                791.80
Glass Jalousie Window SQ.M.                743.02
Sliding Aluminum Window SQ.M.             4,965.09
Swing Type Steel Casement Windows SQ.M.             1,993.03

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other. We simplified it this way for easy price updating.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share

Luzon Doors and Windows Prices

DOORS
Material Description Unit  Amount (PhP)
Accordion Door SQ.M.             2,169.21
Aluminum Glass Door SQ.M.             5,111.61
Flush Hollow Core Door SQ.M.                863.90
Flush Type Solid  Core Door SQ.M.             1,733.05
Glass Transom on Wood SQ.M.             1,792.07
Narra Paneled Type Door SQ.M.             4,981.22
Tanguile Paneled Type Door SQ.M.             3,802.51
Varifold Type Door SQ.M.             3,050.85
WINDOWS
Material Description Unit  Amount (PhP)
Aluminum Casement  Window SQ.M.             4,069.30
Awning Steel Type Casement Windows SQ.M.             1,835.59
Fixed Glass on Metal Frame Window SQ.M.                489.46
Fixed Louvered Steel Window SQ.M.                575.80
Glass Jalousie Window SQ.M.                672.52
Sliding Aluminum Window SQ.M.             4,606.58
Swing Type Steel Casement Windows SQ.M.             1,890.90

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other. We simplified it this way for easy price updating.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share

Average Cost of Septic Tank Construction Philippines

We are getting a lot of  requests about other average construction prices and we are finding time to attend each concerns. This guide should help you (if you do not have any background with construction) as to how much should it cost you to have your own Residential Septic Tanks.

We believe the links below will help you too.

Average Two-Story House Construction Cost

Average House Construction Cost

Bungalow Uno – 36 SQM 2 Bedroom below 500k

Four Rooms Boarding House – 650K ALL-IN

The septic vault plan below comes with its own material price summary.

Sample Septic Tank Plan
Sample Septic Tank Plan
Septic Tank Materials Summary
Description Unit       QTY Amount (PhP)
Excavation cu.m.        6.00         3,000.00
CHB Wall – (18.9 SQ.M.)
100mm thk CHB pcs    245.70         3,931.20
Cement bags        9.92         2,579.85
Sand cu.m.        0.76         1,171.80
Reinforcing Steel kg      61.24         2,939.33
#16 Tie Wire kg        0.95             61.43
Concrete – (2.38 cu.m.)
Gravel including Bed cu.m.        3.00         5,099.49
Sand cu.m.        1.19         1,841.40
Cement bags      21.62         5,621.62
Reinforcing Bars kg    156.20         7,653.56
Plastering Works – (21.6 SQ.M.)
Cement bags        7.13         1,853.28
Sand cu.m.        0.58            903.96
Waterproofing Works – (21.6 SQ.M.)
Cemenitious Waterproofing gal        0.86            777.60
Formworks – (may be used twice)
Formworks & Scaffolds SQ.M.        6.6         2,000.00
Plumbing Works – Septic Vault Only
Pipes and Fittings lot        1.00         1,250.00
>>> GRAND Total       40,684.50

The prices above do not come with the labor cost. Labor cost for this construction should be around 15,000 – 20,000 Php. The timeline for constructing this is 2 weeks at maximum.

If in doubt, it would still be advisable to hire a professional engineer or architect to look over construction.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

Mindanao Metal Roofing Prices

MINDANAO – Metal Roofing Prices
Material Description Unit  Amount (PhP)
Pre-painted Long Span Metal Roofing Sheet, GA 26 SQ.M.               465.97
Pre-painted Metal Roofing Sheet, GA 26 x 2.44m SQ.M.               491.76
Corrugated Roofing, GA 26 – 0.51mm x 2.44m SQ.M.               360.63
Pre-painted Gutter, GA 24 – 0.701mm x 2.44m l.m.               268.05
Ordinary Gutter, GA 24 – 0.701mm x 2.44m l.m.               162.04
Pre-painted Flashing, GA 24 – 0.701mm x 2.44m l.m.               269.73
Ordinary Flashing, GA 24 – 0.701mm x 2.44m l.m.               156.72
Pre-painted Ridge Roll, GA 24 – 0.701mm x 2.44m l.m.               264.34
Ordinary Ridge Roll, GA 24 – 0.701mm x 2.44m l.m.               155.86
Roof Ventilators set            1,370.23

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other. We simplified it this way for easy price updating.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share

Visayas Metal Roofing Prices

VISAYAS – Metal Roofing Prices
Material Description Unit  Amount (PhP)
Pre-painted Long Span Metal Roofing Sheet, GA 26 SQ.M.               506.11
Pre-painted Metal Roofing Sheet, GA 26 x 2.44m SQ.M.               431.99
Corrugated Roofing, GA 26 – 0.51mm x 2.44m SQ.M.               304.83
Pre-painted Gutter, GA 24 – 0.701mm x 2.44m l.m.               245.73
Ordinary Gutter, GA 24 – 0.701mm x 2.44m l.m.               151.72
Pre-painted Flashing, GA 24 – 0.701mm x 2.44m l.m.               223.30
Ordinary Flashing, GA 24 – 0.701mm x 2.44m l.m.               150.10
Pre-painted Ridge Roll, GA 24 – 0.701mm x 2.44m l.m.               246.37
Ordinary Ridge Roll, GA 24 – 0.701mm x 2.44m l.m.               155.11
Roof Ventilators set            1,304.52

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other. We simplified it this way for easy price updating.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share

Luzon Metal Roofing Prices

LUZON – Metal Roofing Prices
Material Description Unit  Amount (PhP)
Pre-painted Long Span Metal Roofing Sheet, GA 26 SQ.M.               397.02
Pre-painted Metal Roofing Sheet, GA 26 x 2.44m SQ.M.               384.65
Corrugated Roofing, GA 26 – 0.51mm x 2.44m SQ.M.               258.80
Pre-painted Gutter, GA 24 – 0.701mm x 2.44m l.m.               191.50
Ordinary Gutter, GA 24 – 0.701mm x 2.44m l.m.               120.86
Pre-painted Flashing, GA 24 – 0.701mm x 2.44m l.m.               187.54
Ordinary Flashing, GA 24 – 0.701mm x 2.44m l.m.               117.11
Pre-painted Ridge Roll, GA 24 – 0.701mm x 2.44m l.m.               188.39
Ordinary Ridge Roll, GA 24 – 0.701mm x 2.44m l.m.               119.40
Roof Ventilators set            1,360.89

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other. We simplified it this way for easy price updating.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share

Mindanao Earthworks and Embankment Prices

MATERIAL DESCRIPTION UNIT  AMOUNT (Php)
EMBANKMENT
Borrow Pit cu.m.          378.34
Mixed Sand & Gravel cu.m.          594.93
Rock cu.m.          671.31
AGGREGATE SUBBASE MATERIALS
Aggregate Subbase Course Material cu.m.          614.52
AGGREGATE BASE COURSE
Crushed Aggregate Base Course cu.m.          711.77
Uncrushed Aggregate Base Course cu.m.          654.30
Blended Weathered Limestone and Crush Stone cu.m.          715.86
Filler Material cu.m.          642.10
LIME STABILIZED ROAD MIXED BASE COURSE
Crushed Lime Stabilized Mix Aggregate Base Course cu.m.          727.06
Uncrushed Lime Stabilized Mix Aggregate Base Course cu.m.          690.95
AGGREGATE SURFACE COURSE
Crushed Aggregate Surface Course cu.m.          714.27
Uncrushed Aggregate Surface Course cu.m.          682.36
BITUMINOUS SURFACE TREATMENT
Crushed Stone Surface Treatment cu.m.          759.71
Crushed Slag  Surface Treatment cu.m.          740.69
Crushed Gravel Surface Treatment cu.m.          728.99

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other. We simplified it this way for easy price updating.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

Visayas Earthworks and Embankment Prices

MATERIAL DESCRIPTION UNIT  AMOUNT (Php)
EMBANKMENT
Borrow Pit cu.m.          391.17
Mixed Sand & Gravel cu.m.          538.28
Rock cu.m.          676.93
AGGREGATE SUBBASE MATERIALS
Aggregate Subbase Course Material cu.m.          614.52
AGGREGATE BASE COURSE
Crushed Aggregate Base Course cu.m.          710.02
Uncrushed Aggregate Base Course cu.m.          665.59
Blended Weathered Limestone and Crush Stone cu.m.          703.96
Filler Material cu.m.          684.51
LIME STABILIZED ROAD MIXED BASE COURSE
Crushed Lime Stabilized Mix Aggregate Base Course cu.m.          694.50
Uncrushed Lime Stabilized Mix Aggregate Base Course cu.m.          650.44
AGGREGATE SURFACE COURSE
Crushed Aggregate Surface Course cu.m.          658.36
Uncrushed Aggregate Surface Course cu.m.          621.58
BITUMINOUS SURFACE TREATMENT
Crushed Stone Surface Treatment cu.m.          731.89
Crushed Slag  Surface Treatment cu.m.          741.59
Crushed Gravel Surface Treatment cu.m.          712.33

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other. We simplified it this way for easy price updating.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

Luzon Earthworks and Embankment Prices

EMBANKMENT
Borrow Pit cu.m.        340.39
Mixed Sand & Gravel cu.m.        420.14
Rock cu.m.        544.67
AGGREGATE SUBBASE MATERIALS
Aggregate Subbase Course Material cu.m.        517.98
AGGREGATE BASE COURSE
Crushed Aggregate Base Course cu.m.        630.38
Uncrushed Aggregate Base Course cu.m.        566.63
Blended Weathered Limestone and Crush Stone cu.m.        581.94
Filler Material cu.m.        483.99
LIME STABILIZED ROAD MIXED BASE COURSE
Crushed Lime Stabilized Mix Aggregate Base Course cu.m.        668.17
Uncrushed Lime Stabilized Mix Aggregate Base Course cu.m.        623.25
AGGREGATE SURFACE COURSE
Crushed Aggregate Surface Course cu.m.        709.36
Uncrushed Aggregate Surface Course cu.m.        618.76
BITUMINOUS SURFACE TREATMENT
Crushed Stone Surface Treatment cu.m.        704.20
Crushed Slag  Surface Treatment cu.m.        701.99
Crushed Gravel Surface Treatment cu.m.        687.15

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other. We simplified it this way for easy price updating.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

Open Basketball Court Construction Price Guide

EARTHWORKS
WORK ITEM DESCRIPTION UNIT  QUANTITY   Unit Price Total Amount
Earthworks
To isolated footing cu.m.                1.22             444.60                 542.41
Backfill and Compaction
To isolated footing cu.m.                4.15             421.20              1,747.98
Hauling and Disposal
To isolated footing cu.m.                2.65             397.80              1,054.17
Gravel Fill
100mm thick gravel bedding to isolated footing cu.m.                0.95         1,764.50              1,676.28
>>>   Sub – Total              5,020.84
CONCRETE FORMWORKS AND ACCESSORIES
WORK ITEM DESCRIPTION UNIT  QUANTITY   Unit Price Total Amount
Structural Cast-in-Place Forms
To isolated footing sq.m.                5.20             660.50              3,434.60
To column sq.m.                6.32             660.50              4,174.36
Concrete Reinforcement Steel – Grade 40
To footing
12mm dia kg              92.09               60.50              5,571.74
To column
12mm dia kg              22.76               60.50              1,376.80
10mm dia kg                5.93               60.50                 358.54
9mm dia kg                6.60               60.50                 399.33
Cast in Place Concrete – Structural Concrete
3,000 PSI
To footing cu.m.                1.70         5,490.40              9,333.68
To column cu.m.                0.54         5,490.40              2,964.82
BASKETBALL COURT ( 16M X 30M X 0.15M THK)
Gravel Bedding (consider 0.15m thk  with 95% compacted) cu.m.              77.00         1,900.00          146,300.00
Concrete (0.15m thick, w/ 2500 psi) cu.m.              72.00         4,920.00          354,240.00
Forms (on sidings) consider: L=92m sq.m.              13.80             650.00              8,970.00
Contraction joint saw-cut groove  with sealant to SOG m              32.00             240.00              7,680.00
Plain Cement Finish sq.m.           480.00             497.25          238,680.00
Reinforcing Bars
10 mm Ø kgs        1,856.28               60.11          111,571.71
16 mm Ø kgs              28.44               60.11              1,709.39
>>>   Sub – Total          896,764.96
FINISHES
Exterior Painting UNIT  QUANTITY   Unit Price Total Amount
To basketball court lines sq.m.              15.22             456.30              6,944.43
To basketball court flooring (Epoxy Painting) sq.m.           448.00             456.30          204,422.40
>>>   Sub – Total          211,366.83
SPECIAL CONSTRUCTION
WORK ITEM DESCRIPTION UNIT  QUANTITY   Unit Price Total Amount
Basketball Stand with Ring set                2.00       17,550.00            35,100.00
>>>   Sub – Total            35,100.00
>>>  GRAND TOTAL       1,148,252.63

VAT not included.

Average construction timeline around 1-3 months.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

https://www.googletagmanager.com/gtag/js?id=UA-146841859-1