Floor Topping and Cement Finish Breakdown per Square Meter

This guide is a materials breakdown per square meter of floor topping and plain cement finish works. All you have to do is to multiply the factors below with your computed total area (in square meter). All in straight-to-the-point calculations.

The floor topping and cement finish in this guide is set at 50mm thickness.

Floor Cement Finish

Materials DescriptionUnitQTY
Cementbag0.73
Sandcu.m.0.06

Floor Topping

Materials DescriptionUnitQTY
CementBag0.70
Sandcu.m.0.06

Floor topping are used in mostly residential projects to rectify slant slab-on-grades and to prepare the floor for tiling works. Should you opt to just use plain cement finish, the cheat sheet above should come handy.


These are shared here for the non-technical people to do their own material computation without the need to ask or hire engineers or quantity surveyors.

Check other construction data with the same concept on the links below.

Partition Walls Materials Breakdown per Square Meter

Roofing Works Materials Breakdown per Square Meter

Painting Works Materials Breakdown per Square Meter

Tiling Works Materials Breakdown per Square Meter

Ceiling Construction Materials Breakdown per Square Meter

Metal Gate Construction Materials Breakdown and Prices

Let us know how this painting per square meter materials breakdown blog helps by liking, sharing or commenting!