This is a bill of quantity price guide to complete installation, testing and commissioning of elevator for a 6-Story building.
GENERAL REQUIREMENTS / PRELIMINARIES | |||
Description | Qty | Unit | Amount (Php) |
A. Mobilization (Temporary Office (including construction/relocation of temporaryfacilities) | |||
Contractor’s Office | 1 | lot | 51,750.00 |
Warehouse | 1 | lot | 51,750.00 |
B. Cleaning and Disposal of Garbage/Debris | 1 | lot | 17,250.00 |
C. Premium for Insurance and Bonds (including Renewal Cost up to Project Completion) | |||
Surety Bond (Equivalent to 10% contract amount) | 1 | lot | 21,968.65 |
Performance Bond (Equivalent to 10% contract amount) | 1 | lot | 43,937.29 |
Guarantee Bond (Equivalent to 10% contract amount) | 1 | lot | 109,814.06 |
D. Water and Electric Consumption | 1 | lot | 23,000.00 |
E. Demobilization (Clearing, removal of temporary facilities, Tools, Debris, Excess Materials, etc.) | 1 | lot | 17,250.00 |
F. Other Requirements (Pls. specify) | |||
Permits (Incl. Mayor’s City tax, & Other Misc. Permit charges) | 1 | lot | 88,895.00 |
Cost of Local Procurement/ Material (Incl. Drawings/ Plotting, PME Sign & Seal materials door safety nettings, barricades, consumable materials, welding rods, wire, etc. | 1 | lot | 492,200.00 |
Cable + Conduit (for WTB-Watch Tower Board or Supervisory Panel | 1 | lot | 34,500.00 |
Total | 952,315.00 |
ELEVATOR WORKS, TESTING & COMMISSIONING | |||
Description | Qty | Unit | Amount (Php) |
Installation of Scaffolding | 1 | lot | 17,503.00 |
Hoisting | 1 | lot | 26,254.50 |
Template Setting | 1 | lot | 43,757.50 |
Marking and Boring of Holes | 1 | lot | 26,254.50 |
Bracket Setting | 1 | lot | 35,006.00 |
Rail Setting | 1 | lot | 43,757.50 |
Sill/Jamb Installation | 1 | lot | 52,509.00 |
Floor Indicator/Call buttons | 1 | lot | 8,751.50 |
Machine Room Equipment Setting | 1 | lot | 43,757.50 |
Machine Room Piping | 1 | lot | 17,503.00 |
Hoist-way Piping | 1 | lot | 43,757.50 |
Landing Door Assembly | 1 | lot | 35,006.00 |
Car Assembly | 1 | lot | 61,260.50 |
Travelling Cable Lay-out | 1 | lot | 21,878.75 |
CWT Assembly | 1 | lot | 21,878.75 |
Lay-out of Ropes | 1 | lot | 26,254.50 |
Wiring (Machine Room/Hoist-way) | 1 | lot | 70,012.00 |
Initial Test | 1 | lot | 52,509.00 |
Slow Speed test (Start up) | 1 | lot | 26,254.50 |
Load Test | 1 | lot | 13,127.25 |
Drop Test | 1 | lot | 13,127.25 |
Buffer Test | 1 | lot | 8,751.50 |
Plate Setting/Slow Switch Installation | 1 | lot | 43,757.50 |
Rubber Block Setting | 1 | lot | 17,503.00 |
High Speed Testing | 1 | lot | 61,260.50 |
Standard/Special Feature Test | 1 | lot | 26,254.50 |
Others | 1 | lot | 17,503.00 |
Total | 875,150.00 |