Philippine Manpower and Equipment Productivity Ratio

PHILIPPINE PRODUCTIVITY RATIOS
DESCRIPTION MANHOUR/UNIT UNIT
1.STRUCTURAL EXCAVATION
Common excavation
Hand 6.00 MH/M3
Machine 0.50 MH/M3
Rock excavation 8.00 MH/M3
Hauling of spoils 1.00 MH/M3
2.STRUCTURAL BACKFILL
By hand 5.00 MH/M3
By machine 2.00 MH/M3
3.TRENCHING
By hand 6.00 MH/M3
By machine 0.50 MH/M3
EXCAVATION- MANUAL
Common earth 8.00 MH/M3
Loam of sand 1.31 MH/M3
Clay or heavy soil 1.64 MH/M3
Rock 2.63 MH/M3
EXCAVATION- MECHANICAL
Common earth 6.67 MH/M3
Rock with jack hammer 16.67 MH/M3
BACKFILLING
Common manual 0.82 MH/M3
Gravel fill manual 5.00 MH/M3
TRENCHING & BACFILLING OF UNDERGROUND PIPING USING EXCAVATION MATLS MANUAL FROM:
0 – 2m Depth 1.25 MH/LM
2 – 3m Depth 1.67 MH/LM
3 – 4m Depth 2.50 MH/LM
4 – 5m Depth 3.33 MH/LM
Placing binder gravel 0.11 MH/M3
Escombro backfilling 0.21 MH/M3
Spreading,tamping & grading 0.48 MH/M2
Mechanical compaction, plate compaction 0.06 MH/M3
MANUAL CLEARING & GRUBBING
Clearing under growth & trees – 12″ 0.05 MH/M2
Clearing under growth & shrubs 0.03 MH/M2
Disposal of soil 1.69 MH/M3
Hauling of soil 1.00 MH/M3
Gravel fill 2.07 MH/M3
EXCAVATION – CRANE & CLAMPSHELL
With 8 men & 2 carpenters 1.07 MH/M3
5.ROOFING AND SIDING
Roofing
Metallic 0.97 MH/m2
Non-Metallic 1.51 MH/m2
Siding
Metallic 1.29 MH/m2
Non-Metallic 1.51 MH/m2
CONCRETE WORKS
4.CONCRETE WORKS
Grade members
Formworks 2.54 MH/M2
Concreting 8.54 MH/M3
Rebar 0.07 MH/kg
Finishing 0.40 MH/M2
Suspended members
Formworks 3.28 MH/M2
Concreting 16.70 MH/M3
Rebar 0.08 MH/kg
Finishing 0.80 MH/M2
Embeded metal 0.27 MH/kg
Water proofing 1.82 MH/M2
Joint filler 0.30 MH/lLm
PLACING CONCRETE
Slab on Fill 5.00 MH/M3
Slip Form 25.00 MH/M3
Floor Finish Unhardened 1.00 MH/M3
Concrete finished hardened 1.43 MH/M3
REBAR WORKS
Ground floor installation 0.07 MH/M3
Upper floor installation 0.08 MH/M3
Fabrication 0.10 MH/M3
Mixing manual 16.00 MH/M3
Mixing machine 1.80 MH/M3
MORE THAN  1.8 M3 POUR
Chute from truck 7.00 MH/M3
Crane & bucket 14.00 MH/M3
Wheeling 27.00 MH/M3
Finishing 2.80 MH/M3
FORMWORKS & CARPENTRY WORKS
FORM WORKS INSTALLATION
Wall on ground 2.00 MH/M2
Wall above ground 2.35 MH/M2
Beams 3.08 MH/M2
Columns 2.35 MH/M2
Suspended slab
Suspended slab 0 – 18″ 1.67 MH/M2
Suspended slab 10 – 36″ up 3.33 MH/M2
Elevated & shored slab forming
Forming only 8.60 MH/M2
Forming & Shoring 11.00 MH/M2
Wood wall & Partition 0.50 MH/M2
FORM WORKS FABRICATION
Form works fabrication 1.00 MH/M2
STRIPPING OF FORMS
Wall on ground 0.25 MH/M2
Wall above 10″ 1.29 MH/M2
Beams 1.03 MH/M2
Columns 0.85 MH/M2
Suspended slab
Suspended slab 0 – 18″ 0.83 MH/M2
Suspended slab 10 – 36″ up 1.08 MH/M2
Elevated & shored slab forming – strip of forms 3.50 MH/M2
Floor slab at grade – strip of forms 2.80 MH/M2
INSTALLATION OF CARPENTRY WORKS
Plywood partition 1.00 MH/PC
T & G Flooring and Siding 0.14 MH/B.F.
Ceiling & frame work 0.36 MH/B.F.
Siding frame work 0.27 MH/B.F.
Flooring framing 0.97 MH/B.F.
Wooden post errection 0.43 MH/B.F.
Truss Fabrication 0.35 MH/B.F.
Truss Installation 0.80 MH/B.F.
Girt Installation 0.21 MH/B.F.
Plates Installation 0.13 MH/B.F.
Purlins Installation 0.27 MH/B.F.
Fascia board Installation 0.46 MH/B.F.
1/4″ or 3/4″ thk. plywood
Cutting by manual 1.00 MH/PC
Assembly 0.42 MH/M2
ARCHITECTURAL SPECIALTIES
DOORS
Wooden 2.37 MH/M2
Steel 7.64 MH/M2
Aluminum 8.07 MH/M2
Cyclone wire 7.64 MH/M2
WINDOWS
Glass 3.23 MH/M2
Louver 4.63 MH/M2
Steel 32.29 MH/M2
PARTITIONS
single wall 2.48 MH/M2
Wooden wall 3.44 MH/M2
Wooden Louver 3.44 MH/M2
cyclone Louver 5.38 MH/M2
PAINTING ( 3 coats )
Equipment 0.24 MH/f2
Pipes 0.30 MH/f2
Miscillaneous 0.24 MH/f2
STRUCTURAL STEEL WORKS
7. STRUCTURAL STEEL
Fabrication
Light 110-130 MH/MT
Heavy 60-90 MH/MT
Errection
Light 70-100 MH/MT
Heavy 40-60 MH/MT
WELDING ( one pass only )
1- Welder and 1- Helper ( 16 total mh ) 40-50 Lf/day
G.1 STRUCTURAL STEEL
Fabrication
Heavy weight 50-90 MH/MT
Light weight 100-125 MH/MT
Grating 1 1/4″ x 3/16″ 3.0 – 3.5 MH/SF
Star threat grating 4.0 – 5.0 MH/SF
Errection
Heavy Structural teel 30 – 60 MH/MT
Light Structural steel 60- 90 MH/MT
Stacks ( Inc. full welding ) 250 – 300 MH/MT
Tanks ( Inc. full welding ) 200 – 275 MH/MT
FINISHING AND MASONRY WORKS
H. CHB
4” CHB
Laying 8.0 – 10 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day
6” CHB
Laying 7.0 – 9.0 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day
8” CHB
Laying 6.0 – 8.0 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day

These are average productivity ratios of an average construction worker. Productivity ratios of manpower and equipment are used in the construction industry to estimate how much time is needed to complete a certain work.

Check this if you are looking for in-budget but outstanding quality powertools.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

32 thoughts on “Philippine Manpower and Equipment Productivity Ratio”

  1. what is the productivity of a labor in a masonry works or in other works, since laying is
    8-10 sq.m/day is it labor included or not? if included how many Thanks

    Reply
    • Hi po Sir Emmanuel, that is 8-10 square meter/day (around 100-120 pcs of CHB per day). Semi-skilled workers normally can install 60-70 pcs of CHB per day. Thanks!

      Reply
  2. Hi good day. pakiclarify naman ang 7. STRUCTURAL STEEL vs G.1 STRUCTURAL STEEL kung ano difference ng dalawa.

    Reply
  3. Thanks!. Your Prices are very helpful. All of these will be more effective if you have the latest updated prices as of late 2019 or 2020.

    More Power!

    Reply
  4. Very informative. Hope you can update the labor cost especially for structural works and kindly include the sheet piles. Thanks

    Reply
  5. Is that values you give is for one worker only? like for example in common excavation by hand..if you said it will be 6MH/m3 then if there are two workers then it will now be 3MH/m3? or am i getting it wrong? thanks

    Reply
  6. Is that manhour/unit is for one worker?like for example in common excavation by hand..if you said that there is 6MH/m3..then if two workers will work then it will now be 3MH/m3? Sorry I’m just a bit lost.. thanks for answering!

    Reply
    • The 6MH/m3 this means that 1 worker can finish the manual excavation in 6hrs in one cubic meter. if you put 2 workers can be done in 3hrs. Therefore, this is realistic.

      Reply

Leave a Reply

https://www.googletagmanager.com/gtag/js?id=UA-146841859-1
%d bloggers like this: