EARTHWORKS | ||||
WORK ITEM DESCRIPTION | UNIT | QUANTITY | Unit Price | Total Amount |
Earthworks | ||||
To isolated footing | cu.m. | 1.22 | 444.60 | 542.41 |
Backfill and Compaction | ||||
To isolated footing | cu.m. | 4.15 | 421.20 | 1,747.98 |
Hauling and Disposal | ||||
To isolated footing | cu.m. | 2.65 | 397.80 | 1,054.17 |
Gravel Fill | ||||
100mm thick gravel bedding to isolated footing | cu.m. | 0.95 | 1,764.50 | 1,676.28 |
>>> Sub – Total | 5,020.84 |
CONCRETE FORMWORKS AND ACCESSORIES | ||||
WORK ITEM DESCRIPTION | UNIT | QUANTITY | Unit Price | Total Amount |
Structural Cast-in-Place Forms | ||||
To isolated footing | sq.m. | 5.20 | 660.50 | 3,434.60 |
To column | sq.m. | 6.32 | 660.50 | 4,174.36 |
Concrete Reinforcement Steel – Grade 40 | ||||
To footing | ||||
12mm dia | kg | 92.09 | 60.50 | 5,571.74 |
To column | ||||
12mm dia | kg | 22.76 | 60.50 | 1,376.80 |
10mm dia | kg | 5.93 | 60.50 | 358.54 |
9mm dia | kg | 6.60 | 60.50 | 399.33 |
Cast in Place Concrete – Structural Concrete | ||||
3,000 PSI | ||||
To footing | cu.m. | 1.70 | 5,490.40 | 9,333.68 |
To column | cu.m. | 0.54 | 5,490.40 | 2,964.82 |
BASKETBALL COURT ( 16M X 30M X 0.15M THK) | ||||
Gravel Bedding (consider 0.15m thk with 95% compacted) | cu.m. | 77.00 | 1,900.00 | 146,300.00 |
Concrete (0.15m thick, w/ 2500 psi) | cu.m. | 72.00 | 4,920.00 | 354,240.00 |
Forms (on sidings) consider: L=92m | sq.m. | 13.80 | 650.00 | 8,970.00 |
Contraction joint saw-cut groove with sealant to SOG | m | 32.00 | 240.00 | 7,680.00 |
Plain Cement Finish | sq.m. | 480.00 | 497.25 | 238,680.00 |
Reinforcing Bars | ||||
10 mm Ø | kgs | 1,856.28 | 60.11 | 111,571.71 |
16 mm Ø | kgs | 28.44 | 60.11 | 1,709.39 |
>>> Sub – Total | 896,764.96 |
FINISHES | ||||
Exterior Painting | UNIT | QUANTITY | Unit Price | Total Amount |
To basketball court lines | sq.m. | 15.22 | 456.30 | 6,944.43 |
To basketball court flooring (Epoxy Painting) | sq.m. | 448.00 | 456.30 | 204,422.40 |
>>> Sub – Total | 211,366.83 |
SPECIAL CONSTRUCTION | ||||
WORK ITEM DESCRIPTION | UNIT | QUANTITY | Unit Price | Total Amount |
Basketball Stand with Ring | set | 2.00 | 17,550.00 | 35,100.00 |
>>> Sub – Total | 35,100.00 | |||
>>> GRAND TOTAL | 1,148,252.63 |
VAT not included.
Average construction timeline around 1-3 months.
To see all the material prices we have posted click here.
Please let us know how this blog helped you by subscribing, hitting like or share!