Philippine Manpower and Equipment Productivity Ratio

PHILIPPINE PRODUCTIVITY RATIOS
DESCRIPTION MANHOUR/UNIT UNIT
1.STRUCTURAL EXCAVATION
Common excavation
Hand 6.00 MH/M3
Machine 0.50 MH/M3
Rock excavation 8.00 MH/M3
Hauling of spoils 1.00 MH/M3
2.STRUCTURAL BACKFILL
By hand 5.00 MH/M3
By machine 2.00 MH/M3
3.TRENCHING
By hand 6.00 MH/M3
By machine 0.50 MH/M3
EXCAVATION- MANUAL
Common earth 8.00 MH/M3
Loam of sand 1.31 MH/M3
Clay or heavy soil 1.64 MH/M3
Rock 2.63 MH/M3
EXCAVATION- MECHANICAL
Common earth 6.67 MH/M3
Rock with jack hammer 16.67 MH/M3
BACKFILLING
Common manual 0.82 MH/M3
Gravel fill manual 5.00 MH/M3
TRENCHING & BACFILLING OF UNDERGROUND PIPING USING EXCAVATION MATLS MANUAL FROM:
0 – 2m Depth 1.25 MH/LM
2 – 3m Depth 1.67 MH/LM
3 – 4m Depth 2.50 MH/LM
4 – 5m Depth 3.33 MH/LM
Placing binder gravel 0.11 MH/M3
Escombro backfilling 0.21 MH/M3
Spreading,tamping & grading 0.48 MH/M2
Mechanical compaction, plate compaction 0.06 MH/M3
MANUAL CLEARING & GRUBBING
Clearing under growth & trees – 12″ 0.05 MH/M2
Clearing under growth & shrubs 0.03 MH/M2
Disposal of soil 1.69 MH/M3
Hauling of soil 1.00 MH/M3
Gravel fill 2.07 MH/M3
EXCAVATION – CRANE & CLAMPSHELL
With 8 men & 2 carpenters 1.07 MH/M3
5.ROOFING AND SIDING
Roofing
Metallic 0.97 MH/m2
Non-Metallic 1.51 MH/m2
Siding
Metallic 1.29 MH/m2
Non-Metallic 1.51 MH/m2
CONCRETE WORKS
4.CONCRETE WORKS
Grade members
Formworks 2.54 MH/M2
Concreting 8.54 MH/M3
Rebar 0.07 MH/kg
Finishing 0.40 MH/M2
Suspended members
Formworks 3.28 MH/M2
Concreting 16.70 MH/M3
Rebar 0.08 MH/kg
Finishing 0.80 MH/M2
Embeded metal 0.27 MH/kg
Water proofing 1.82 MH/M2
Joint filler 0.30 MH/lLm
PLACING CONCRETE
Slab on Fill 5.00 MH/M3
Slip Form 25.00 MH/M3
Floor Finish Unhardened 1.00 MH/M3
Concrete finished hardened 1.43 MH/M3
REBAR WORKS
Ground floor installation 0.07 MH/M3
Upper floor installation 0.08 MH/M3
Fabrication 0.10 MH/M3
Mixing manual 16.00 MH/M3
Mixing machine 1.80 MH/M3
MORE THAN  1.8 M3 POUR
Chute from truck 7.00 MH/M3
Crane & bucket 14.00 MH/M3
Wheeling 27.00 MH/M3
Finishing 2.80 MH/M3
FORMWORKS & CARPENTRY WORKS
FORM WORKS INSTALLATION
Wall on ground 2.00 MH/M2
Wall above ground 2.35 MH/M2
Beams 3.08 MH/M2
Columns 2.35 MH/M2
Suspended slab
Suspended slab 0 – 18″ 1.67 MH/M2
Suspended slab 10 – 36″ up 3.33 MH/M2
Elevated & shored slab forming
Forming only 8.60 MH/M2
Forming & Shoring 11.00 MH/M2
Wood wall & Partition 0.50 MH/M2
FORM WORKS FABRICATION
Form works fabrication 1.00 MH/M2
STRIPPING OF FORMS
Wall on ground 0.25 MH/M2
Wall above 10″ 1.29 MH/M2
Beams 1.03 MH/M2
Columns 0.85 MH/M2
Suspended slab
Suspended slab 0 – 18″ 0.83 MH/M2
Suspended slab 10 – 36″ up 1.08 MH/M2
Elevated & shored slab forming – strip of forms 3.50 MH/M2
Floor slab at grade – strip of forms 2.80 MH/M2
INSTALLATION OF CARPENTRY WORKS
Plywood partition 1.00 MH/PC
T & G Flooring and Siding 0.14 MH/B.F.
Ceiling & frame work 0.36 MH/B.F.
Siding frame work 0.27 MH/B.F.
Flooring framing 0.97 MH/B.F.
Wooden post errection 0.43 MH/B.F.
Truss Fabrication 0.35 MH/B.F.
Truss Installation 0.80 MH/B.F.
Girt Installation 0.21 MH/B.F.
Plates Installation 0.13 MH/B.F.
Purlins Installation 0.27 MH/B.F.
Fascia board Installation 0.46 MH/B.F.
1/4″ or 3/4″ thk. plywood
Cutting by manual 1.00 MH/PC
Assembly 0.42 MH/M2
ARCHITECTURAL SPECIALTIES
DOORS
Wooden 2.37 MH/M2
Steel 7.64 MH/M2
Aluminum 8.07 MH/M2
Cyclone wire 7.64 MH/M2
WINDOWS
Glass 3.23 MH/M2
Louver 4.63 MH/M2
Steel 32.29 MH/M2
PARTITIONS
single wall 2.48 MH/M2
Wooden wall 3.44 MH/M2
Wooden Louver 3.44 MH/M2
cyclone Louver 5.38 MH/M2
PAINTING ( 3 coats )
Equipment 0.24 MH/f2
Pipes 0.30 MH/f2
Miscillaneous 0.24 MH/f2
STRUCTURAL STEEL WORKS
7. STRUCTURAL STEEL
Fabrication
Light 110-130 MH/MT
Heavy 60-90 MH/MT
Errection
Light 70-100 MH/MT
Heavy 40-60 MH/MT
WELDING ( one pass only )
1- Welder and 1- Helper ( 16 total mh ) 40-50 Lf/day
G.1 STRUCTURAL STEEL
Fabrication
Heavy weight 50-90 MH/MT
Light weight 100-125 MH/MT
Grating 1 1/4″ x 3/16″ 3.0 – 3.5 MH/SF
Star threat grating 4.0 – 5.0 MH/SF
Errection
Heavy Structural teel 30 – 60 MH/MT
Light Structural steel 60- 90 MH/MT
Stacks ( Inc. full welding ) 250 – 300 MH/MT
Tanks ( Inc. full welding ) 200 – 275 MH/MT
FINISHING AND MASONRY WORKS
H. CHB
4” CHB
Laying 8.0 – 10 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day
6” CHB
Laying 7.0 – 9.0 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day
8” CHB
Laying 6.0 – 8.0 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day

These are average productivity ratios of an average construction worker. Productivity ratios of manpower and equipment are used in the construction industry to estimate how much time is needed to complete a certain work.

Check this if you are looking for in-budget but outstanding quality powertools.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

32 thoughts on “Philippine Manpower and Equipment Productivity Ratio”

  1. Hi, can I ask for the source of this? Any government association that released these rates? Thank you so much, I need this for my research.

    Reply
  2. what does B.F stand for? board feet? if so then for truss fabrication and installation is for wooden truss and not steel

    Reply

Leave a Reply

https://www.googletagmanager.com/gtag/js?id=UA-146841859-1

Discover more from PHILCON PRICES

Subscribe now to keep reading and get access to the full archive.

Continue reading