Average Construction Cost for Two-Story Houses in the Philippines

A friend told us that there are a lot of Filipinos who want to know the average price of house construction in the Philippines. For simplicity, most engineers would only say per square meter price of the house, roughly 20,000-25,000 Pesos. True, those prices are close to reality but is too vague for a layman’s point of view.

Check the latest and another house plan with breakdown for average construction cost for two story residential unit here!

For sure clients want actual numbers. Like how much would the construction of ceiling be, the tiling works, the foundation and others. This is a detailed bill of quantity for an average Filipino to know how much would it need to construct their two-story houses. This is inspired from one of our actual projects. the construction materials cost is as of 2019 prices.

The floor plan below corresponds to the detailed bill of quantity after it.

Average 2 Story House Sample - Ground Floor
average
Work Breakdown StructureAmount (PhP)Rel. Wtd (%)
Preliminaries
Preliminaries₱95,150.002.70%
I. Structural Works
Foundation₱99,012.772.81%
Ground Floor₱237,570.346.74%
Second Floor₱200,043.145.68%
>>> sub total₱536,626.2515.23%
Metal Works
 Roof Framing – Truss Works₱322,321.219.14%
 Metal Fabrication (Steel gratings/capping, drain area)₱39,692.581.13%
 Metal Railings (To Balcony and stairs)₱59,910.311.70%
>>> sub total₱421,924.1011.97%
II. Architectural Works
Masonry
 Exterior Wall – (and Firewall)  
 Ground Floor (Including stiffiner columns and lintel beams)₱80,201.242.28%
 Second Floor (Including stiffiner columns and lintel beams)₱101,196.322.87%
 Interior Wall  
 Ground Floor₱66,420.581.88%
 Second Floor₱101,681.422.88%
>>> sub total₱349,499.569.92%
Finishes
 Cement Plastering
 to exterior wall   
 Ground Floor₱25,459.220.72%
 Second Floor₱25,737.790.73%
 To Interior Wall   
 Ground Floor₱36,023.111.02%
 Second Floor₱46,258.041.31%
>>> sub total₱133,478.163.79%
 Painting Works
 Ceiling Boards  
 Exterior₱16,030.520.45%
 Interior₱33,114.220.94%
 Elastomeric Paint  
 to exterior wall₱68,252.151.94%
 to interior wall₱78,076.132.22%
>>> sub total₱195,473.015.55%
 Ceiling Works  
 Exterior Ceiling Boards₱57,969.241.64%
 Interior Ceiling Boards₱85,837.262.44%
>>> sub total₱143,806.504.08%
 Thermal and Moisture Protection
 Dampoofing and Waterproofing Works (Toilet and terrace)₱28,877.900.82%
 Roof Insulation – including roofing shingles, gutter, ridge, etc.₱289,290.758.21%
>>> sub total₱318,168.659.03%
 Tiling Works₱205,159.065.82%
 Cabinetry, Caseworks and Countertops₱55,435.751.57%
 Doors and Windows₱150,977.594.28%
 Wood, Plastics and Composites₱89,817.452.55%
 Glazing Works (Shower enclosure, glass balustrade on terrace)₱81,174.852.30%
 Specialties  (Toilet and bath accessories)₱6,537.040.19%
III. Plumbing Works
Domestic Waterline₱54,219.001.54%
Sanitary and Drainage₱85,517.002.43%
Facility Septic Tank₱55,180.001.57%
Storm Line₱30,024.000.85%
Plumbing Fixtures₱39,979.001.13%
>>> sub total₱264,919.007.52%
IV. Heating, Ventilation and Air Conditioning (HVAC)
Testing, Adjusting and Balancing for HVAC₱16,098.790.46%
HVAC Pipings – Refrigerant Pipes, Condensate Drain and Insulations₱18,982.880.54%
HVAC Ducts and Casings (Kitchen exhaust, ducts and vents on comfort rooms),₱38,393.461.09%
HVAC Fans and Blowers₱11,793.600.33%
>>> sub total₱85,268.732.42%
V. Electrical Works
Grounding and Bonding with support & consumables₱10,797.300.31%
Low Voltage Electrical Power Conductors & Cables₱121,545.723.45%
Raceway & Boxes₱38,890.251.10%
Commissioning of Electrical Systems₱8,750.000.25%
Switchboards and Panelboards₱27,083.100.77%
Electricity Metering₱11,249.280.32%
Wiring Devices₱44,709.511.27%
Interior Lighting₱56,118.751.59%
>>> sub total₱319,143.919.05%
Communications
Grounding and Bonding with support & consumables₱13,162.500.37%
Voice and Data Communications₱19,828.330.56%
Audio-Video Communications, CATV System₱22,006.750.62%
>>> sub total₱54,997.581.56%
Electronic Safety and Security – Fire Detection/Alarm₱5,096.000.14%
External Works₱11,963.690.34%
>>> GRAND TOTAL₱3,524,616.86100.00%

This is a mid-range cost house. Average timeline for this house from the excavation to finishing is around 8 months to 12 months.  The prices above comes with the labor, materials and equipment cost.

We’ve scouted a site with good customer reviews for their hand tools on this site, they ship nationwide!

If you are looking for a metal gate construction, click here.

We have also created posts that most people asks us about. Check it out below.

 

Bungalow Uno

Four Rooms Boarding House – 650K ALL-IN

Roofing Works Materials Breakdown per Square Meter

Tiling Works Materials Breakdown per Square Meter

Ceiling Construction Materials Breakdown per Square Meter

This is only a guide and you will need a professional technical person to asses the cost based on your location. Anyhow, let us know how this post helped you by commenting, liking and sharing! 

57 thoughts on “Average Construction Cost for Two-Story Houses in the Philippines”

  1. With this data, an average price per cubic meter can be calculated quite well, but nowhere is it stated how many square meters the floors have together or individually. That would be important information.

    Reply
  2. hello po mgkno po kya mgagastos ko s labors s 2 storey house 4 bedrooms finish po…?mga ilang months po kya un mttpos?slmat po

    Reply
    • Hello Madame Majorie,

      Need po ng plano maam, para malaman yung 1. Cost ng materials at labor, at 2. Construction timeline. Mas maigi po maam mag-inquire kayo sa any professional near you

      Reply
  3. I like your floor plan can you give me a price on that floorplan thank you sincerely Howard Soares

    Reply

Leave a Reply

https://www.googletagmanager.com/gtag/js?id=UA-146841859-1

Discover more from PHILCON PRICES

Subscribe now to keep reading and get access to the full archive.

Continue reading