EARTHWORKS | ||||
WORK ITEM DESCRIPTION | UNIT | QUANTITY | Unit Price | Total Amount |
Earthworks | ||||
To isolated footing | cu.m. | 1.22 | 444.60 | 542.41 |
Backfill and Compaction | ||||
To isolated footing | cu.m. | 4.15 | 421.20 | 1,747.98 |
Hauling and Disposal | ||||
To isolated footing | cu.m. | 2.65 | 397.80 | 1,054.17 |
Gravel Fill | ||||
100mm thick gravel bedding to isolated footing | cu.m. | 0.95 | 1,764.50 | 1,676.28 |
>>> Sub – Total | 5,020.84 |
CONCRETE FORMWORKS AND ACCESSORIES | ||||
WORK ITEM DESCRIPTION | UNIT | QUANTITY | Unit Price | Total Amount |
Structural Cast-in-Place Forms | ||||
To isolated footing | sq.m. | 5.20 | 660.50 | 3,434.60 |
To column | sq.m. | 6.32 | 660.50 | 4,174.36 |
Concrete Reinforcement Steel – Grade 40 | ||||
To footing | ||||
12mm dia | kg | 92.09 | 60.50 | 5,571.74 |
To column | ||||
12mm dia | kg | 22.76 | 60.50 | 1,376.80 |
10mm dia | kg | 5.93 | 60.50 | 358.54 |
9mm dia | kg | 6.60 | 60.50 | 399.33 |
Cast in Place Concrete – Structural Concrete | ||||
3,000 PSI | ||||
To footing | cu.m. | 1.70 | 5,490.40 | 9,333.68 |
To column | cu.m. | 0.54 | 5,490.40 | 2,964.82 |
BASKETBALL COURT ( 16M X 30M X 0.15M THK) | ||||
Gravel Bedding (consider 0.15m thk with 95% compacted) | cu.m. | 77.00 | 1,900.00 | 146,300.00 |
Concrete (0.15m thick, w/ 2500 psi) | cu.m. | 72.00 | 4,920.00 | 354,240.00 |
Forms (on sidings) consider: L=92m | sq.m. | 13.80 | 650.00 | 8,970.00 |
Contraction joint saw-cut groove with sealant to SOG | m | 32.00 | 240.00 | 7,680.00 |
Plain Cement Finish | sq.m. | 480.00 | 497.25 | 238,680.00 |
Reinforcing Bars | ||||
10 mm Ø | kgs | 1,856.28 | 60.11 | 111,571.71 |
16 mm Ø | kgs | 28.44 | 60.11 | 1,709.39 |
>>> Sub – Total | 896,764.96 |
FINISHES | ||||
Exterior Painting | UNIT | QUANTITY | Unit Price | Total Amount |
To basketball court lines | sq.m. | 15.22 | 456.30 | 6,944.43 |
To basketball court flooring (Epoxy Painting) | sq.m. | 448.00 | 456.30 | 204,422.40 |
>>> Sub – Total | 211,366.83 |
SPECIAL CONSTRUCTION | ||||
WORK ITEM DESCRIPTION | UNIT | QUANTITY | Unit Price | Total Amount |
Basketball Stand with Ring | set | 2.00 | 17,550.00 | 35,100.00 |
>>> Sub – Total | 35,100.00 | |||
>>> GRAND TOTAL | 1,148,252.63 |
VAT not included.
Average construction timeline around 1-3 months.
To see all the material prices we have posted click here.
Please let us know how this blog helped you by subscribing, hitting like or share!
how much the cost if covered court with the same size? Thanks
how many square meter ?
Hi Ms. Annabel, standard size 15mx28m po yung court, but (16mx30m) or 480sqm po yung total area. Thank you and stay safe 🙂
How much the cost if covered po with the same dimension