Open Basketball Court Construction Price Guide

EARTHWORKS
WORK ITEM DESCRIPTION UNIT  QUANTITY   Unit Price Total Amount
Earthworks
To isolated footing cu.m.                1.22             444.60                 542.41
Backfill and Compaction
To isolated footing cu.m.                4.15             421.20              1,747.98
Hauling and Disposal
To isolated footing cu.m.                2.65             397.80              1,054.17
Gravel Fill
100mm thick gravel bedding to isolated footing cu.m.                0.95         1,764.50              1,676.28
>>>   Sub – Total              5,020.84
CONCRETE FORMWORKS AND ACCESSORIES
WORK ITEM DESCRIPTION UNIT  QUANTITY   Unit Price Total Amount
Structural Cast-in-Place Forms
To isolated footing sq.m.                5.20             660.50              3,434.60
To column sq.m.                6.32             660.50              4,174.36
Concrete Reinforcement Steel – Grade 40
To footing
12mm dia kg              92.09               60.50              5,571.74
To column
12mm dia kg              22.76               60.50              1,376.80
10mm dia kg                5.93               60.50                 358.54
9mm dia kg                6.60               60.50                 399.33
Cast in Place Concrete – Structural Concrete
3,000 PSI
To footing cu.m.                1.70         5,490.40              9,333.68
To column cu.m.                0.54         5,490.40              2,964.82
BASKETBALL COURT ( 16M X 30M X 0.15M THK)
Gravel Bedding (consider 0.15m thk  with 95% compacted) cu.m.              77.00         1,900.00          146,300.00
Concrete (0.15m thick, w/ 2500 psi) cu.m.              72.00         4,920.00          354,240.00
Forms (on sidings) consider: L=92m sq.m.              13.80             650.00              8,970.00
Contraction joint saw-cut groove  with sealant to SOG m              32.00             240.00              7,680.00
Plain Cement Finish sq.m.           480.00             497.25          238,680.00
Reinforcing Bars
10 mm Ø kgs        1,856.28               60.11          111,571.71
16 mm Ø kgs              28.44               60.11              1,709.39
>>>   Sub – Total          896,764.96
FINISHES
Exterior Painting UNIT  QUANTITY   Unit Price Total Amount
To basketball court lines sq.m.              15.22             456.30              6,944.43
To basketball court flooring (Epoxy Painting) sq.m.           448.00             456.30          204,422.40
>>>   Sub – Total          211,366.83
SPECIAL CONSTRUCTION
WORK ITEM DESCRIPTION UNIT  QUANTITY   Unit Price Total Amount
Basketball Stand with Ring set                2.00       17,550.00            35,100.00
>>>   Sub – Total            35,100.00
>>>  GRAND TOTAL       1,148,252.63

VAT not included.

Average construction timeline around 1-3 months.

To see all the material prices we have posted click here.

Please let us know how this blog helped you by subscribing, hitting like or share!

4 thoughts on “Open Basketball Court Construction Price Guide”

    • Hi Ms. Annabel, standard size 15mx28m po yung court, but (16mx30m) or 480sqm po yung total area. Thank you and stay safe 🙂

      Reply

Leave a Reply

https://www.googletagmanager.com/gtag/js?id=UA-146841859-1

Discover more from PHILCON PRICES

Subscribe now to keep reading and get access to the full archive.

Continue reading